FINERACT-2148: Process monetary transaction after zero interest charge-off.
This commit is contained in:
committed by
Adam Saghy
parent
23850a1b73
commit
faaf44d91a
@@ -1920,4 +1920,208 @@ Feature: Charge-off
|
||||
| 01 January 2023 | Disbursement | 100.0 | 0.0 | 0.0 | 0.0 | 0.0 | 100.0 |
|
||||
| 14 February 2023 | Charge-off | 100.85 | 100.0 | 0.85 | 0.0 | 0.0 | 0.0 |
|
||||
|
||||
Scenario: Charge-off on due date when loan behaviour is zero-interest and interestRecalculation - repayment after charge off
|
||||
When Admin sets the business date to "1 January 2024"
|
||||
And Admin creates a client with random data
|
||||
And Admin creates a fully customized loan with the following data:
|
||||
| LoanProduct | submitted on date | with Principal | ANNUAL interest rate % | interest type | interest calculation period | amortization type | loanTermFrequency | loanTermFrequencyType | repaymentEvery | repaymentFrequencyType | numberOfRepayments | graceOnPrincipalPayment | graceOnInterestPayment | interest free period | Payment strategy |
|
||||
| LP2_ADV_PYMNT_INTEREST_DAILY_INTEREST_RECALCULATION_ZERO_INTEREST_CHARGE_OFF_BEHAVIOUR | 01 January 2024 | 100 | 7 | DECLINING_BALANCE | DAILY | EQUAL_INSTALLMENTS | 6 | MONTHS | 1 | MONTHS | 6 | 0 | 0 | 0 | ADVANCED_PAYMENT_ALLOCATION |
|
||||
Then Loan Repayment schedule has 6 periods, with the following data for periods:
|
||||
| Nr | Days | Date | Paid date | Balance of loan | Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| | | 01 January 2024 | | 100.0 | | | 0.0 | | 0.0 | | | | 0.0 |
|
||||
| 1 | 31 | 01 February 2024 | | 83.57 | 16.43 | 0.58 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 2 | 29 | 01 March 2024 | | 67.05 | 16.52 | 0.49 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 3 | 31 | 01 April 2024 | | 50.43 | 16.62 | 0.39 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 4 | 30 | 01 May 2024 | | 33.71 | 16.72 | 0.29 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 5 | 31 | 01 June 2024 | | 16.9 | 16.81 | 0.2 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 6 | 30 | 01 July 2024 | | 0.0 | 16.9 | 0.1 | 0.0 | 0.0 | 17.0 | 0.0 | 0.0 | 0.0 | 17.0 |
|
||||
Then Loan Repayment schedule has the following data in Total row:
|
||||
| Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| 100 | 2.05 | 0 | 0 | 102.05 | 0 | 0 | 0 | 102.05 |
|
||||
And Admin successfully approves the loan on "1 January 2024" with "100" amount and expected disbursement date on "1 January 2024"
|
||||
And Admin successfully disburse the loan on "1 January 2024" with "100" EUR transaction amount
|
||||
When Admin sets the business date to "1 February 2024"
|
||||
And Customer makes "AUTOPAY" repayment on "01 February 2024" with 17.01 EUR transaction amount
|
||||
Then Loan Repayment schedule has 6 periods, with the following data for periods:
|
||||
| Nr | Days | Date | Paid date | Balance of loan | Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| | | 01 January 2024 | | 100.0 | | | 0.0 | | 0.0 | 0.0 | | | |
|
||||
| 1 | 31 | 01 February 2024 | 01 February 2024 | 83.57 | 16.43 | 0.58 | 0.0 | 0.0 | 17.01 | 17.01 | 0.0 | 0.0 | 0.0 |
|
||||
| 2 | 29 | 01 March 2024 | | 67.05 | 16.52 | 0.49 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 3 | 31 | 01 April 2024 | | 50.43 | 16.62 | 0.39 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 4 | 30 | 01 May 2024 | | 33.71 | 16.72 | 0.29 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 5 | 31 | 01 June 2024 | | 16.9 | 16.81 | 0.2 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 6 | 30 | 01 July 2024 | | 0.0 | 16.9 | 0.1 | 0.0 | 0.0 | 17.0 | 0.0 | 0.0 | 0.0 | 17.0 |
|
||||
Then Loan Repayment schedule has the following data in Total row:
|
||||
| Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| 100 | 2.05 | 0 | 0 | 102.05 | 17.01| 0 | 0 | 85.04 |
|
||||
When Admin sets the business date to "29 February 2024"
|
||||
And Admin does charge-off the loan on "29 February 2024"
|
||||
Then Loan Repayment schedule has 6 periods, with the following data for periods:
|
||||
| Nr | Days | Date | Paid date | Balance of loan | Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| | | 01 January 2024 | | 100.0 | | | 0.0 | | 0.0 | 0.0 | | | |
|
||||
| 1 | 31 | 01 February 2024 | 01 February 2024 | 83.57 | 16.43 | 0.58 | 0.0 | 0.0 | 17.01 | 17.01 | 0.0 | 0.0 | 0.0 |
|
||||
| 2 | 29 | 01 March 2024 | | 67.03 | 16.54 | 0.47 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 3 | 31 | 01 April 2024 | | 50.02 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 4 | 30 | 01 May 2024 | | 33.01 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 5 | 31 | 01 June 2024 | | 16.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 6 | 30 | 01 July 2024 | | 0.0 | 16.0 | 0.0 | 0.0 | 0.0 | 16.0 | 0.0 | 0.0 | 0.0 | 16.0 |
|
||||
Then Loan Repayment schedule has the following data in Total row:
|
||||
| Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| 100 | 1.05 | 0 | 0 | 101.05 | 17.01 | 0 | 0 | 84.04 |
|
||||
Then Loan Transactions tab has the following data:
|
||||
| Transaction date | Transaction Type | Amount | Principal | Interest | Fees | Penalties | Loan Balance | Reverted | Replayed |
|
||||
| 01 January 2024 | Disbursement | 100.0 | 0.0 | 0.0 | 0.0 | 0.0 | 100.0 | false | false |
|
||||
| 01 February 2024 | Repayment | 17.01 | 16.43 | 0.58 | 0.0 | 0.0 | 83.57 | false | false |
|
||||
| 29 February 2024 | Charge-off | 84.04 | 83.57 | 0.47 | 0.0 | 0.0 | 0.0 | false | false |
|
||||
# ----- repayment after charge off on 1st March ----- #
|
||||
When Admin sets the business date to "01 March 2024"
|
||||
And Customer makes "AUTOPAY" repayment on "01 March 2024" with 17.01 EUR transaction amount
|
||||
Then Loan Repayment schedule has 6 periods, with the following data for periods:
|
||||
| Nr | Days | Date | Paid date | Balance of loan | Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| | | 01 January 2024 | | 100.0 | | | 0.0 | | 0.0 | 0.0 | | | |
|
||||
| 1 | 31 | 01 February 2024 | 01 February 2024 | 83.57 | 16.43 | 0.58 | 0.0 | 0.0 | 17.01 | 17.01 | 0.0 | 0.0 | 0.0 |
|
||||
| 2 | 29 | 01 March 2024 | 01 March 2024 | 67.03 | 16.54 | 0.47 | 0.0 | 0.0 | 17.01 | 17.01 | 0.0 | 0.0 | 0.0 |
|
||||
| 3 | 31 | 01 April 2024 | | 50.02 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 4 | 30 | 01 May 2024 | | 33.01 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 5 | 31 | 01 June 2024 | | 16.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 6 | 30 | 01 July 2024 | | 0.0 | 16.0 | 0.0 | 0.0 | 0.0 | 16.0 | 0.0 | 0.0 | 0.0 | 16.0 |
|
||||
Then Loan Repayment schedule has the following data in Total row:
|
||||
| Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| 100 | 1.05 | 0 | 0 | 101.05 | 34.02 | 0 | 0 | 67.03 |
|
||||
Then Loan Transactions tab has the following data:
|
||||
| Transaction date | Transaction Type | Amount | Principal | Interest | Fees | Penalties | Loan Balance | Reverted | Replayed |
|
||||
| 01 January 2024 | Disbursement | 100.0 | 0.0 | 0.0 | 0.0 | 0.0 | 100.0 | false | false |
|
||||
| 01 February 2024 | Repayment | 17.01 | 16.43 | 0.58 | 0.0 | 0.0 | 83.57 | false | false |
|
||||
| 29 February 2024 | Charge-off | 84.04 | 83.57 | 0.47 | 0.0 | 0.0 | 0.0 | false | false |
|
||||
| 01 March 2024 | Repayment | 17.01 | 16.54 | 0.47 | 0.0 | 0.0 | 67.03 | false | false |
|
||||
|
||||
@PS-2137-s5
|
||||
Scenario: Charge-off on due date when loan behaviour is zero-interest and interestRecalculation - charge off after one installment is overdue (31st March)
|
||||
When Admin sets the business date to "1 January 2024"
|
||||
And Admin creates a client with random data
|
||||
And Admin creates a fully customized loan with the following data:
|
||||
| LoanProduct | submitted on date | with Principal | ANNUAL interest rate % | interest type | interest calculation period | amortization type | loanTermFrequency | loanTermFrequencyType | repaymentEvery | repaymentFrequencyType | numberOfRepayments | graceOnPrincipalPayment | graceOnInterestPayment | interest free period | Payment strategy |
|
||||
| LP2_ADV_PYMNT_INTEREST_DAILY_INTEREST_RECALCULATION_ZERO_INTEREST_CHARGE_OFF_BEHAVIOUR | 01 January 2024 | 100 | 7 | DECLINING_BALANCE | DAILY | EQUAL_INSTALLMENTS | 6 | MONTHS | 1 | MONTHS | 6 | 0 | 0 | 0 | ADVANCED_PAYMENT_ALLOCATION |
|
||||
Then Loan Repayment schedule has 6 periods, with the following data for periods:
|
||||
| Nr | Days | Date | Paid date | Balance of loan | Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| | | 01 January 2024 | | 100.0 | | | 0.0 | | 0.0 | | | | 0.0 |
|
||||
| 1 | 31 | 01 February 2024 | | 83.57 | 16.43 | 0.58 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 2 | 29 | 01 March 2024 | | 67.05 | 16.52 | 0.49 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 3 | 31 | 01 April 2024 | | 50.43 | 16.62 | 0.39 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 4 | 30 | 01 May 2024 | | 33.71 | 16.72 | 0.29 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 5 | 31 | 01 June 2024 | | 16.9 | 16.81 | 0.2 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 6 | 30 | 01 July 2024 | | 0.0 | 16.9 | 0.1 | 0.0 | 0.0 | 17.0 | 0.0 | 0.0 | 0.0 | 17.0 |
|
||||
Then Loan Repayment schedule has the following data in Total row:
|
||||
| Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| 100 | 2.05 | 0 | 0 | 102.05 | 0 | 0 | 0 | 102.05 |
|
||||
And Admin successfully approves the loan on "1 January 2024" with "100" amount and expected disbursement date on "1 January 2024"
|
||||
And Admin successfully disburse the loan on "1 January 2024" with "100" EUR transaction amount
|
||||
When Admin sets the business date to "1 February 2024"
|
||||
And Customer makes "AUTOPAY" repayment on "01 February 2024" with 17.01 EUR transaction amount
|
||||
Then Loan Repayment schedule has 6 periods, with the following data for periods:
|
||||
| Nr | Days | Date | Paid date | Balance of loan | Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| | | 01 January 2024 | | 100.0 | | | 0.0 | | 0.0 | 0.0 | | | |
|
||||
| 1 | 31 | 01 February 2024 | 01 February 2024 | 83.57 | 16.43 | 0.58 | 0.0 | 0.0 | 17.01 | 17.01 | 0.0 | 0.0 | 0.0 |
|
||||
| 2 | 29 | 01 March 2024 | | 67.05 | 16.52 | 0.49 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 3 | 31 | 01 April 2024 | | 50.43 | 16.62 | 0.39 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 4 | 30 | 01 May 2024 | | 33.71 | 16.72 | 0.29 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 5 | 31 | 01 June 2024 | | 16.9 | 16.81 | 0.2 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 6 | 30 | 01 July 2024 | | 0.0 | 16.9 | 0.1 | 0.0 | 0.0 | 17.0 | 0.0 | 0.0 | 0.0 | 17.0 |
|
||||
Then Loan Repayment schedule has the following data in Total row:
|
||||
| Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| 100 | 2.05 | 0 | 0 | 102.05 | 17.01| 0 | 0 | 85.04 |
|
||||
When Admin sets the business date to "31 March 2024"
|
||||
And Admin does charge-off the loan on "31 March 2024"
|
||||
Then Loan Repayment schedule has 6 periods, with the following data for periods:
|
||||
| Nr | Days | Date | Paid date | Balance of loan | Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| | | 01 January 2024 | | 100.0 | | | 0.0 | | 0.0 | 0.0 | | | |
|
||||
| 1 | 31 | 01 February 2024 | 01 February 2024 | 83.57 | 16.43 | 0.58 | 0.0 | 0.0 | 17.01 | 17.01 | 0.0 | 0.0 | 0.0 |
|
||||
| 2 | 29 | 01 March 2024 | | 67.05 | 16.52 | 0.49 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 3 | 31 | 01 April 2024 | | 50.51 | 16.54 | 0.47 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 4 | 30 | 01 May 2024 | | 33.5 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 5 | 31 | 01 June 2024 | | 16.49 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 6 | 30 | 01 July 2024 | | 0.0 | 16.49 | 0.0 | 0.0 | 0.0 | 16.49 | 0.0 | 0.0 | 0.0 | 16.49 |
|
||||
Then Loan Repayment schedule has the following data in Total row:
|
||||
| Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| 100 | 1.54 | 0 | 0 | 101.54 | 17.01 | 0 | 0 | 84.53 |
|
||||
Then Loan Transactions tab has the following data:
|
||||
| Transaction date | Transaction Type | Amount | Principal | Interest | Fees | Penalties | Loan Balance | Reverted | Replayed |
|
||||
| 01 January 2024 | Disbursement | 100.0 | 0.0 | 0.0 | 0.0 | 0.0 | 100.0 | false | false |
|
||||
| 01 February 2024 | Repayment | 17.01 | 16.43 | 0.58 | 0.0 | 0.0 | 83.57 | false | false |
|
||||
| 31 March 2024 | Charge-off | 84.53 | 83.57 | 0.96 | 0.0 | 0.0 | 0.0 | false | false |
|
||||
|
||||
@PS-2137-s6
|
||||
Scenario: Charge-off on due date when loan behaviour is zero-interest and interestRecalculation - backdated repayment
|
||||
When Admin sets the business date to "1 January 2024"
|
||||
And Admin creates a client with random data
|
||||
And Admin creates a fully customized loan with the following data:
|
||||
| LoanProduct | submitted on date | with Principal | ANNUAL interest rate % | interest type | interest calculation period | amortization type | loanTermFrequency | loanTermFrequencyType | repaymentEvery | repaymentFrequencyType | numberOfRepayments | graceOnPrincipalPayment | graceOnInterestPayment | interest free period | Payment strategy |
|
||||
| LP2_ADV_PYMNT_INTEREST_DAILY_INTEREST_RECALCULATION_ZERO_INTEREST_CHARGE_OFF_BEHAVIOUR | 01 January 2024 | 100 | 7 | DECLINING_BALANCE | DAILY | EQUAL_INSTALLMENTS | 6 | MONTHS | 1 | MONTHS | 6 | 0 | 0 | 0 | ADVANCED_PAYMENT_ALLOCATION |
|
||||
Then Loan Repayment schedule has 6 periods, with the following data for periods:
|
||||
| Nr | Days | Date | Paid date | Balance of loan | Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| | | 01 January 2024 | | 100.0 | | | 0.0 | | 0.0 | | | | 0.0 |
|
||||
| 1 | 31 | 01 February 2024 | | 83.57 | 16.43 | 0.58 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 2 | 29 | 01 March 2024 | | 67.05 | 16.52 | 0.49 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 3 | 31 | 01 April 2024 | | 50.43 | 16.62 | 0.39 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 4 | 30 | 01 May 2024 | | 33.71 | 16.72 | 0.29 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 5 | 31 | 01 June 2024 | | 16.9 | 16.81 | 0.2 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 6 | 30 | 01 July 2024 | | 0.0 | 16.9 | 0.1 | 0.0 | 0.0 | 17.0 | 0.0 | 0.0 | 0.0 | 17.0 |
|
||||
Then Loan Repayment schedule has the following data in Total row:
|
||||
| Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| 100 | 2.05 | 0 | 0 | 102.05 | 0 | 0 | 0 | 102.05 |
|
||||
And Admin successfully approves the loan on "1 January 2024" with "100" amount and expected disbursement date on "1 January 2024"
|
||||
And Admin successfully disburse the loan on "1 January 2024" with "100" EUR transaction amount
|
||||
When Admin sets the business date to "1 February 2024"
|
||||
And Customer makes "AUTOPAY" repayment on "01 February 2024" with 17.01 EUR transaction amount
|
||||
Then Loan Repayment schedule has 6 periods, with the following data for periods:
|
||||
| Nr | Days | Date | Paid date | Balance of loan | Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| | | 01 January 2024 | | 100.0 | | | 0.0 | | 0.0 | 0.0 | | | |
|
||||
| 1 | 31 | 01 February 2024 | 01 February 2024 | 83.57 | 16.43 | 0.58 | 0.0 | 0.0 | 17.01 | 17.01 | 0.0 | 0.0 | 0.0 |
|
||||
| 2 | 29 | 01 March 2024 | | 67.05 | 16.52 | 0.49 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 3 | 31 | 01 April 2024 | | 50.43 | 16.62 | 0.39 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 4 | 30 | 01 May 2024 | | 33.71 | 16.72 | 0.29 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 5 | 31 | 01 June 2024 | | 16.9 | 16.81 | 0.2 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 6 | 30 | 01 July 2024 | | 0.0 | 16.9 | 0.1 | 0.0 | 0.0 | 17.0 | 0.0 | 0.0 | 0.0 | 17.0 |
|
||||
Then Loan Repayment schedule has the following data in Total row:
|
||||
| Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| 100 | 2.05 | 0 | 0 | 102.05 | 17.01| 0 | 0 | 85.04 |
|
||||
When Admin sets the business date to "31 March 2024"
|
||||
And Admin does charge-off the loan on "31 March 2024"
|
||||
Then Loan Repayment schedule has 6 periods, with the following data for periods:
|
||||
| Nr | Days | Date | Paid date | Balance of loan | Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| | | 01 January 2024 | | 100.0 | | | 0.0 | | 0.0 | 0.0 | | | |
|
||||
| 1 | 31 | 01 February 2024 | 01 February 2024 | 83.57 | 16.43 | 0.58 | 0.0 | 0.0 | 17.01 | 17.01 | 0.0 | 0.0 | 0.0 |
|
||||
| 2 | 29 | 01 March 2024 | | 67.05 | 16.52 | 0.49 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 3 | 31 | 01 April 2024 | | 50.51 | 16.54 | 0.47 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 4 | 30 | 01 May 2024 | | 33.5 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 5 | 31 | 01 June 2024 | | 16.49 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 6 | 30 | 01 July 2024 | | 0.0 | 16.49 | 0.0 | 0.0 | 0.0 | 16.49 | 0.0 | 0.0 | 0.0 | 16.49 |
|
||||
Then Loan Repayment schedule has the following data in Total row:
|
||||
| Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| 100 | 1.54 | 0 | 0 | 101.54 | 17.01 | 0 | 0 | 84.53 |
|
||||
Then Loan Transactions tab has the following data:
|
||||
| Transaction date | Transaction Type | Amount | Principal | Interest | Fees | Penalties | Loan Balance | Reverted | Replayed |
|
||||
| 01 January 2024 | Disbursement | 100.0 | 0.0 | 0.0 | 0.0 | 0.0 | 100.0 | false | false |
|
||||
| 01 February 2024 | Repayment | 17.01 | 16.43 | 0.58 | 0.0 | 0.0 | 83.57 | false | false |
|
||||
| 31 March 2024 | Charge-off | 84.53 | 83.57 | 0.96 | 0.0 | 0.0 | 0.0 | false | false |
|
||||
# ----- backdated repayment on 1 March made on 31 March ----- #
|
||||
And Customer makes "AUTOPAY" repayment on "01 March 2024" with 17.01 EUR transaction amount
|
||||
Then Loan Repayment schedule has 6 periods, with the following data for periods:
|
||||
| Nr | Days | Date | Paid date | Balance of loan | Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| | | 01 January 2024 | | 100.0 | | | 0.0 | | 0.0 | 0.0 | | | |
|
||||
| 1 | 31 | 01 February 2024 | 01 February 2024 | 83.57 | 16.43 | 0.58 | 0.0 | 0.0 | 17.01 | 17.01 | 0.0 | 0.0 | 0.0 |
|
||||
| 2 | 29 | 01 March 2024 | 01 March 2024 | 67.05 | 16.52 | 0.49 | 0.0 | 0.0 | 17.01 | 17.01 | 0.0 | 0.0 | 0.0 |
|
||||
| 3 | 31 | 01 April 2024 | | 50.42 | 16.63 | 0.38 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 4 | 30 | 01 May 2024 | | 33.41 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 5 | 31 | 01 June 2024 | | 16.4 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 | 0.0 | 0.0 | 0.0 | 17.01 |
|
||||
| 6 | 30 | 01 July 2024 | | 0.0 | 16.4 | 0.0 | 0.0 | 0.0 | 16.4 | 0.0 | 0.0 | 0.0 | 16.4 |
|
||||
Then Loan Repayment schedule has the following data in Total row:
|
||||
| Principal due | Interest | Fees | Penalties | Due | Paid | In advance | Late | Outstanding |
|
||||
| 100 | 1.45 | 0 | 0 | 101.45 | 34.02 | 0 | 0 | 67.43 |
|
||||
Then Loan Transactions tab has the following data:
|
||||
| Transaction date | Transaction Type | Amount | Principal | Interest | Fees | Penalties | Loan Balance | Reverted | Replayed |
|
||||
| 01 January 2024 | Disbursement | 100.0 | 0.0 | 0.0 | 0.0 | 0.0 | 100.0 | false | false |
|
||||
| 01 February 2024 | Repayment | 17.01 | 16.43 | 0.58 | 0.0 | 0.0 | 83.57 | false | false |
|
||||
| 01 March 2024 | Repayment | 17.01 | 16.52 | 0.49 | 0.0 | 0.0 | 67.05 | false | false |
|
||||
| 31 March 2024 | Charge-off | 67.43 | 67.05 | 0.38 | 0.0 | 0.0 | 0.0 | false | true |
|
||||
|
||||
|
||||
+4
-3
@@ -1175,6 +1175,7 @@ public class AdvancedPaymentScheduleTransactionProcessor extends AbstractLoanRep
|
||||
if (LoanChargeOffBehaviour.ZERO_INTEREST.equals(loanTransaction.getLoan().getLoanProductRelatedDetail().getChargeOffBehaviour())
|
||||
&& !loanTransaction.isReversed()) {
|
||||
handleZeroInterestChargeOff(loanTransaction, progressiveTransactionCtx);
|
||||
progressiveTransactionCtx.setChargedOff(true);
|
||||
}
|
||||
}
|
||||
|
||||
@@ -1583,7 +1584,7 @@ public class AdvancedPaymentScheduleTransactionProcessor extends AbstractLoanRep
|
||||
transactionMappings, loanTransaction, oldestPastDueInstallment, currency);
|
||||
Loan loan = loanTransaction.getLoan();
|
||||
if (transactionCtx instanceof ProgressiveTransactionCtx ctx && loan.isInterestBearing()
|
||||
&& loan.getLoanProductRelatedDetail().isInterestRecalculationEnabled()) {
|
||||
&& loan.getLoanProductRelatedDetail().isInterestRecalculationEnabled() && !ctx.isChargedOff()) {
|
||||
paidPortion = handlingPaymentAllocationForInterestBearingProgressiveLoan(loanTransaction,
|
||||
transactionAmountUnprocessed, balances, paymentAllocationType, oldestPastDueInstallment, ctx,
|
||||
loanTransactionToRepaymentScheduleMapping, oldestPastDueInstallmentCharges);
|
||||
@@ -1605,7 +1606,7 @@ public class AdvancedPaymentScheduleTransactionProcessor extends AbstractLoanRep
|
||||
transactionMappings, loanTransaction, dueInstallment, currency);
|
||||
Loan loan = loanTransaction.getLoan();
|
||||
if (transactionCtx instanceof ProgressiveTransactionCtx ctx && loan.isInterestBearing()
|
||||
&& loan.getLoanProductRelatedDetail().isInterestRecalculationEnabled()) {
|
||||
&& loan.getLoanProductRelatedDetail().isInterestRecalculationEnabled() && !ctx.isChargedOff()) {
|
||||
paidPortion = handlingPaymentAllocationForInterestBearingProgressiveLoan(loanTransaction,
|
||||
transactionAmountUnprocessed, balances, paymentAllocationType, dueInstallment, ctx,
|
||||
loanTransactionToRepaymentScheduleMapping, dueInstallmentCharges);
|
||||
@@ -1636,7 +1637,7 @@ public class AdvancedPaymentScheduleTransactionProcessor extends AbstractLoanRep
|
||||
|
||||
Loan loan = loanTransaction.getLoan();
|
||||
if (transactionCtx instanceof ProgressiveTransactionCtx ctx && loan.isInterestBearing()
|
||||
&& loan.getLoanProductRelatedDetail().isInterestRecalculationEnabled()) {
|
||||
&& loan.getLoanProductRelatedDetail().isInterestRecalculationEnabled() && !ctx.isChargedOff()) {
|
||||
paidPortion = handlingPaymentAllocationForInterestBearingProgressiveLoan(loanTransaction, evenPortion,
|
||||
balances, paymentAllocationType, inAdvanceInstallment, ctx,
|
||||
loanTransactionToRepaymentScheduleMapping, inAdvanceInstallmentCharges);
|
||||
|
||||
+2
@@ -43,6 +43,8 @@ public class ProgressiveTransactionCtx extends TransactionCtx {
|
||||
private List<LoanTransaction> alreadyProcessedTransactions = new ArrayList<>();
|
||||
@Setter
|
||||
private Money sumOfInterestRefundAmount;
|
||||
@Setter
|
||||
private boolean isChargedOff = false;
|
||||
|
||||
public ProgressiveTransactionCtx(MonetaryCurrency currency, List<LoanRepaymentScheduleInstallment> installments,
|
||||
Set<LoanCharge> charges, MoneyHolder overpaymentHolder, ChangedTransactionDetail changedTransactionDetail,
|
||||
|
||||
Reference in New Issue
Block a user